Sanitation Project : Partnership Of Assessment Answer

Describe about the Sanitation Project for Partnership of Businesses.

Answer:

Brief Summary of the Project:

The major objective of this program is to improve the cleanliness and to get rid of the litterity that the household sectors that litter on the roads. This project will take place under the Improve City Sanitation group (ICS-group) in partnership with Shuddhi a registered Non-Governmental Organization. Sanitation has been a major concern in Mumbai Metropolitan Region over the years prompting groups like “SMART-CITY” to try managing the situation (Ashwini, 2015; Burra, 2005). Reports indicate the need to sanitize Mumbai town (Vaidya, & Srivastva, 2010; Zahanggir, Alinur, & A


bdullah, 2013). This menace has cost the municipality huge sums of money in the name of waste management (Yedla, & Kansal, 2003).

The ICS-group program will be done in Mumbai and with time can be absorbed by other towns which are in need of cleanliness and litter management such as New Delhi.

Project aim: Addressing the main problem which is littering and Tackling the problem of garbage disposal

Project objectives:

To promote cleanliness, waste management and better hygiene by bin placement.

To curb open defecation by providing adequate and accessible sanitation services.

To implement the waste to energy project.

To form initiatives which benefit the community from a clean environment

Project strategies

Forming steering committees of the group

Traveling to Mumbai to review the sanitation situation

Recruiting volunteers for the program

Allocation of roles and duties to group members

Monitor and evaluate implementation of the program 

Trial the model in 1 pilot site

Training the participants in the program

Project key personnel: ICS-group members and Shudhi

Key project stakeholders: The chair of Mumbai Metropolitan Region

Project sustainability consideration: In order to sustain the benefits of the project, several actions and strategies have been put in place. For instance, the project design involves selecting a team of members who would travel to the site to assess the current situation there firsts. Also, the committee steering the project shall receive adequate training for better implementation of the project.

Project Strategies

Strategies

Key activities

Time frame for each activity

Positions involved

Responsible person

Forming steering committees

·         Kick start the project activities

10/01/2016-10/02/2016

ICS-group

Shudhi

ICS-group Head

Training the participants in the program

·         Seminars on sanitation

12/02/2016-12/04/2016

Program trainers

Trainer head   

Traveling to Mumbai to

·         Reviewing  the sanitation situation in Mumbai

14/04/2016-20/04/2016

ICS-group members

Project head

Roles and duties allocation  

·         Assigning roles to members of the program

27/04/2016-30/04/2016

 

ICS-group members

 

Project head

 

Recruiting volunteers for the program

·         Interviews to selects locals to participate in the project

1/05/2016-2/06/2016

 

ICS-group members

 

ICS-group members

Program piloting  

·         Trial the model in pilot site

5/06/2016-3/10/2016

ICS-group members

Project head

Monitor and evaluate implementation of the program

·         Checking effectiveness of the program in Mumbai by interviewing locals

4/10/2016-1/01/2017

ICS-group members and Shudhi

project head

 

 

 


Project Process Evaluation

key evaluation

questions

Indicators of

achievements/Success

indicators

Methods for

measurement

including details of

data collection

When will the

information be

collected

Responsible

person

Has open defection reduced?

Absence of feces in open areas

 

Interviewing residents

At the start and end of project

Project head

How often are bins used?

Bins installed around the road are full

No traces of litter on the road

Manually checking the bins

 

At the start and end of project

Project head

There will be a comparison between the initial baseline exercise and the current situation within three months. There will be monitoring of the rates of open defecation and also the functionality of the bins that will be installed in close proximity in the town. There will be photographic records taken as time passes with the continuing of the project.

Impact Evaluation

Objectives

Indicators of

achievements/

Success indicators

Methods for

Measurements

including details of data

collection

When

should data

collection

and analysis

take place?

Responsible

person

To promote cleanliness and waste management

Full waste bins

Interviews

Start and of project

ICS-head

To curb open defecation

No feces in the open

 keeping records 

End of project

ICS-head

To implement the waste to energy project

Litters like wood used for cooking

Observations

End of project

ICS-head

To form initiatives which benefit the community from a clean environment

 

Willingness of many locals to volunteer in the program

Interviews

Record keeping 

Start and end of project

Shudhi coordinator

 

References

Ashwini Save, Akshay Abhyankar, Harshit Damani, & Ashwini Bhoir. (2015). “SMART CITY”: Municipal Corporation Services for Human Welfare. IJERT, V4(05). doi:10.17577/ijertv4is050483

Burra, S. (2005). Towards a pro-poor framework for slum upgrading in Mumbai, India. Environment and Urbanization, 17(1), 67-88. doi:10.1630/0956247053633700

Vaidya, C., & Srivastva, S. (2010). Mumbai Human Development Report 2009, (Municipal Corporation of Greater Mumbai), 2009. Environment and Urbanization Asia, 1(2), 229-229. doi:10.1177/097542531000100214

Van Dijk, T., Bhide, A., & Shivtare, V. (2016). When a participatory slum sanitation project encounters urban informality: The case of the Greater Mumbai Metropolitan Region. International Area Studies Review, 19(1), 45-59. doi:10.1177/2233865916628701

Yedla, S., & Kansal, S. (2003). Economic insight into municipal solid waste management in Mumbai: a critical analysis. International Journal of Environment and Pollution, 19(5), 516. doi:10.1504/ijep.2003.004329

Zahanggir Alam, M., Alinur Rahman, M., & Abdullah Al Firoz, M. (2013). Water Supply and Sanitation Facilities in Urban Slums: A Case Study of Rajshahi City Corporation Slums. American Journal of Civil Engineering and Architecture, 1(1), 1-6. doi:10.12691/ajcea-1-1-1



Buy Sanitation Project : Partnership Of Assessment Answers Online

Talk to our expert to get the help with Sanitation Project : Partnership Of Assessment Answers from Assignment Hippo Experts to complete your assessment on time and boost your grades now

The main aim/motive of the finance assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignment help Australia. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at www.assignmenthippo.com are so much skilled, capable, talented, and experienced in their field and use our best and free Citation Generator and cite your writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Sanitation Project : Partnership Of Assessment Answer Assignment Help Online

Want to order fresh copy of the Sample Sanitation Project : Partnership Of Assessment Answers? online or do you need the old solutions for Sample Sanitation Project : Partnership Of Assessment Answer, contact our customer support or talk to us to get the answers of it.

Assignment Help Australia
Want latest solution of this assignment

Want to order fresh copy of the Sanitation Project : Partnership Of Assessment Answers? online or do you need the old solutions for Sample Sanitation Project : Partnership Of Assessment Answer, contact our customer support or talk to us to get the answers of it.