Acc00716 Financial Management - Free Assessment Answer

Pinto Limited has recently been subject to significant competition from overseas manufacturers with much lower costs. To combat this, Pinto is considering a project that will see it move into a new product market considered riskier than its current operations. The CEO has asked you to undertake a financial analysis of the proposed project and present your recommendations in a short memo. As part of your financial analysis you will calculate NPV, IRR, payback period, discounted payback period and profitability index.
The project requires an upfront investment in plant and equipment of $15 million, which will be depreciated on a straight-line basis over the five-year life of the project. The equipment is not expected to have any significant salvage value at the end of its depreciable life. Pinto paid $25,000 in fees to consultants for a market analysis related to the project. This analysis predicted sales volume of 200,000 units in the first year, which would grow by 50% per year in years two and three, and fall by 50% in each remaining year as demand wanes. Selling price in the first year is expected to be $75 and grow by 3% each year after that.
Pinto’s operations manager has estimated cost of goods sold for the project will equal 60% of sales revenues and selling, general and administrative expenses directly related to the project (excluding depreciation) will be $1 million in the first year and increase by 5% per year thereafter. The operations manager has not included in his estimates any cost for a project operations base because the plan is to use a building the company already owns. Currently Pinto rents this building to another company for $250,000 per year.
The project will require an upfront investment in net working capital equal to 20% of the year 1 sales revenue forecast. This investment in working capital will be fully recovered at the end year 5.

Answer:

Introduction:

There has been a proposal on the part of the company to launch a new product as the current product offering of the company is witnessing high competition on declining cost concerns. The significance of this memo needs to be understood in this backdrop since this memo highlights the analysis of the proposed project using various tools and techniques so as to comment on the underlying financial feasibility. The key information about the project expected cash flow has been taken into consideration to derive the incremental post tax cash flows which form the basis for further analysis. Besides, considering the risky nature of the project and uncertainty with regards to consumer response, uncertainty analysis has also been performed. This highlights the financial robustness of the project under adverse input conditions.  With regards to computation of project cash flows the following aspects have been considered.

  • Since various capital budgeting measures are based on discounted cash flows, hence there is a need to compute the present value of the future cash flows arising from the project. In reality, these cash flows for a given year would arise at different times. But to make the computation simpler, it is assumed that all project related cash flows tend to take place at project life end (Petty et. al., 2015).
  • The company that as per the proposed project details would serve as the manufacturing base is currently being used by outside party and the company realises rental income annually to the extent of $ 250,000. If the company does decide to go ahead with the project, then one incremental cash outflow would be the reduction of rental income which ought to be considered as an operational expense for the project since now the same rent has to be paid for factory use considering arm length transaction (Damodaran, 2015).
  • Also, considering a new product line, hence the company has taken the services of a external consultant but the fees given to him/her would not be part of the incremental cash flows. This is because it is a sunk cost for this project since without regards to the decision taken, the fee cannot be obtained back from the consultant (Brealey, Myers and  Allen, 2014).

Alter tax Project Cash Flows

The cash flows arising from the proposed project are listed as follows in a tabular format.

In relation of the cash flow in base case, the financial feasibility can be ascertained using capital budgeting tools. The result of the computation of these parameters as indicated in the attached spreadsheet is shared below along with the decision in relation to the given project.

Uncertainty Analysis

The project has successfully demonstrated financial feasibility in the base case but owing to the risk involved in the project, it is essential to analyse the underlying change in NPV when the key input variable display unfavourable movement. Two variables that would be considered in this analysis are as follows.

  • Project discount rate – This has been selected owing to risk of project being higher than the usual projects which puts an upward pressure on the discount rate adversely impacting project feasibility.
  • Growth rate of unit sales – The company is launching a new product and despite the prediction by external consultant there is risk with regards to the response received by customers.

The following two techniques have been used.

  • Scenario Analysis

The two possible scenarios along with their underlying assumptions are explained below.

.Optimistic Scenario

Estimates probability of this scenario = 0.25

The key assumptions include unit growth rate at 70%, 60%, -40%, -40% for year 2, 3, 4,5 respectively.

Computed NPV by making the above changes as highlighted in the attached spreadsheet comes out as $10.70 million

Pessimistic Scenario

Estimates probability of this scenario = 0.35

The key assumptions include unit growth rate at 35%, 25%, -60%, -70% for year 2, 3, 4,5 respectively. Also, there is hike in discount rate to 13.5%.

Computed NPV by making the above changes as highlighted in the attached spreadsheet comes out as -$0.79 million

Expected NPV computation = 0.25*10.70 + 0.4*5.6 + 0.35*(-0.79) = $4.64 million

  • Sensitivity Analysis

The NPV movement as the above two variables i.e. discount rate and the unit volume growth in year 2 and year 23 continue to change is captured in the graph shown below.

From the above graph, there is immense resilience in the NPV which does get impacted by the variables chosen. However, for the NPV to become negative the adverse movement in these variables has to be sizable and the corresponding likelihood of this happening is quite remote thus implying that the project is robust enough to stay NPV position even under possible adverse circumstances (Petty et. al, 2015).

Recommendation

The financial analysis clearly signifies that the proposed project is feasible on the financial front and this is not only limited to the base case but also successfully would accommodate possible adverse movements in key variables. Therefore, it is in the shareholders’ interest that project implementation must commence at the earliest and during implementation, the various changes in the input variables used in the financial model must be reflected so that possible adjustments can be made if required  (Parrino and Kidwell, 2014).

References

Brealey, R. A., Myers, S. C., & Allen, F. (2014) Principles of corporate finance, 2nd ed. New York: McGraw-Hill Inc.

Damodaran, A. (2015). Applied corporate finance: A user’s manual 3rd ed. New York: Wiley, John & Sons.

Parrino, R. and Kidwell, D. (2014) Fundamentals of Corporate Finance, 3rd ed. London: Wiley Publications

Petty, J.W., Titman, S., Keown, A., Martin, J.D., Martin, P., Burrow, M., & Nguyen, H. (2015). Financial Management, Principles and Applications, 6th ed..  NSW: Pearson Education, French Forest Australia.


Buy Acc00716 Financial Management - Free Assessment Answers Online

Talk to our expert to get the help with Acc00716 Financial Management - Free Assessment Answers from Assignment Hippo Experts to complete your assessment on time and boost your grades now

The main aim/motive of the finance assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignment help Australia. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at www.assignmenthippo.com are so much skilled, capable, talented, and experienced in their field and use our best and free Citation Generator and cite your writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Acc00716 Financial Management - Free Assessment Answer Assignment Help Online

Want to order fresh copy of the Sample Acc00716 Financial Management - Free Assessment Answers? online or do you need the old solutions for Sample Acc00716 Financial Management - Free Assessment Answer, contact our customer support or talk to us to get the answers of it.

Assignment Help Australia
Want latest solution of this assignment

Want to order fresh copy of the Acc00716 Financial Management - Free Assessment Answers? online or do you need the old solutions for Sample Acc00716 Financial Management - Free Assessment Answer, contact our customer support or talk to us to get the answers of it.